"Turboatom" in late March, arranged and provided products to representatives of six power plants

26.03.2019

In late March, JSC "Turboatom" arranged and provided products to representatives of six power plants: South-Ukrainian, Zaporizhzhya NPP, Kozloduy NPP, as well as Dnipro-2 HPP, Seredniodniprovska and Kanev HPPs.

According to results of delivery of products, for condenser of South-Ukrainian NPP, turbine condenser units for unit No. 3 were shipped: 16 modules, chambers, parts of casings No. 2.3, as well as other equipment as a whole according to order. For Kozloduy NPP, units of upgraded flow part of high pressure cylinder of turbine of Unit No 5 (set of diaphragms, splitter damper and equipment) have been shipped – high pressure rotor is being manufactured, delivery of which is planned for NPP representatives in coming days.

For the second turbine of Kanev HPP, oil head and servomotors are delivered and are awaiting for shipment; work continues on manufacture of equipment for the third turbine. For Dnipro-2 HPP as a whole, control assembly of distributor was delivered, production workshops started disassembling and preparing parts and assemblies for shipment. Runner chamber has been delivered to representatives of Seredniodniprovska HPP - "embedded parts" stage is generally ready for shipment under order.