Movses Vardanyan, General Director of CJSC “Armenian Nuclear Power Plant”, expressed his gratitude to Viktor Subotin, General Director of JSC “Turboatom”, for a set of works on the modernization of the K-220-44-1 turbine unit of NPP.
In particular, the letter says: “As part of the modernization of the Armenian NPP power unit, in November 2018 and September 2019, turbine unit No. 3 and No. 4 of power unit No. 2 were put into operation.
We express our gratitude to You and the entire team of JSC “Turboatom” for the whole set of ongoing modernization work of the K-220-44-1 turbine unit.
For the timely and high-quality manufacture of components, the modernization of parts, the ability to quickly and efficiently solve emerging issues of varying complexity, we thank the design team, production teams, quality control and production management.
We emphasize the professional and high-quality fulfillment of the installation supervision of the modernized turbine assemblies as planned. We look forward to further successful and fruitful cooperation with Your enterprise. "
Note. In early October of this year, “Turboatom” fully fulfilled its obligations under the contract for the supply of equipment to the Metsamor (Armenian) NPP, which was concluded in March 2017.
According to the contract, “Turboatom” has modernized two K-220-44 turbines with a rated capacity of 220 MW each at power unit No. 2 of the nuclear power plant.
Modernization made it possible to obtain a power increase, increase the overhaul period and extend the life of the turbines.