A work on equipment for hydroelectric power plants, the modernization of which is carried out under contracts with PrJSC“Ukrhydroenergo” and with funds from European banks continuesat JSC “Turboatom”.
In particular, in workshop No. 83 they are completing assembling a distributor for Kaniv HPP (station 18). On April 7, equipment is being prepared for delivery to the customer. Also, in the same workshop, the runner for Dnipro-2 HPP (station 14) is assembled and ready for delivery to the customer.
It is worth reminding that, according to the relevant contract the enterprise will manufacture and supply 7 fully-equipped 7 ПЛ 15-ГК-600 hydraulic turbines for the reconstruction of two power units of Kaniv HPP. The first four hydraulic units under this agreement were completely shipped to the station.
According to the contract, the reconstruction of two hydraulic units is planned for Dnipro-2 HPP. The equipment of one of the hydraulic units (station 16) was completely shipped to the station.