A commissioning of equipment for three stations subordinate to “Ukrhydroenergo”areat the final stage at “Turboatom”

15.04.2020

The work on the production of equipment for stations subordinate to PrJSC“Ukrhydroenergo” is ongoing in the workshops of JSC “Turboatom”

Workshop No. 72 of JSC“Turboatom” prepared for shipment the runner chamber for Seredniodniprovska HPP (station 1). All reporting documentation on the stage of embedded parts has already been transferred to the customer.

Also the delivery of equipment for Dnipro-2 HPP (station 14) isat the final stage.The 1st stage of passing functional tests of the runner is at the stage of coordination with the customer. At the moment, the runner is being prepared for final balancing and further shipment.

The work on manufacture of a distributor for Kaniv HPP (station 18) was completed. Now the work on the final painting and packaging for shipment is underway in the workshops.

It is worth reminding thatin 2011 the European Bank for Reconstruction and Development (EBRD) and the European Investment Bank (EIB), at the request of “Ukrhydroenergo”, decided to provide a loan totaling 400 million euros for the implementation of the project for the reconstruction of hydraulic power plants in Ukraine, including 7 units of Kaniv HPP, 3 units of Kyiv PSPP, 2 units of Kremenchug HPP, 2 units of Seredniodniprovska HPP and 2 units of Dnipro-2 HPP. According to the terms of the loan, international competitive biddings were held in which Kharkiv“Turboatom” in contract with the SE “PlantElektrotyazhmash”won.