The action plan includes preparation of power supply utilities, machine tools, buildings, structures, vehicles, lifting and transport equipment, warehousing and social facilities.
According to Chief Engineer of "Turboatom" Grigoriy Ishchenko, main work on preparation for winter will begin in mid-May. "Engineering and construction services are auditing and, if necessary, repairing factory networks and communications. Main equipment in need of repair work will be repaired according to separate schedules," - he said.
In addition, current repairs of heat system, heating, lighting and ventilation systems, main drinking water pipelines, thermal furnaces, transformers are planned. Also repairs of roof, sidewalks, roads are provided.
All work to prepare for autumn-winter period must be completed by 1 October 2020, after which General Director will approve passport of enterprise readiness for winter.