EN
UA

A work on distributors for Kyiv PSPP and Dnipro-2 HPP is continued at “Turboatom”

22.05.2020

A work on distributors for Kyiv PSPP and Dnipro-2 HPP is continued at “Turboatom”. Work is scheduled to be completed before the end of summer 2020. In addition, the workshops began work on the 2nd stage of delivery the runner for Dnipro-2 HPP.

The runner for Kaniv HPP (station 18) has already been shipped to the station, now the delivery and shipment of the distributoris at the final stage.

It is worth reminding thatthe commissioning after the reconstruction of hydraulic unit No. 2 at Kyiv PSPP took place on July 16, 2019, and on May 14, 2020, the hydraulic unit No. 6 was put into trial operation. The reconstruction of the hydraulic unit station No. 4 of Kyiv PSPP is planned to be completed in January 2021.

The work is carried out according to the contract for the reconstruction of hydraulic units of Kyiv PSPP No. 2, 6, 4 for the funds of the European Investment Bank and the European Bank for Reconstruction and Development.