Work on equipment for Ukrainian hydroelectric power plants is underway in “Turboatom's” workshops

09.06.2020

In workshops of JSC “Turboatom” production of main units for hydraulic unit No4 of Kyiv PSPP is close to completion. In particular, in workshop No73 began final balancing of runner. In workshop No 83 final machining of turbine head cover is close to completion and distributor is prepared for its installation and subsequent control assembly. Task of production is to complete work on this order and prepare products for delivery in July this year.

Runner for Dnipro-2 HPP (station 14) was completely delivered to the customer and plant started its shipping to power plant. It is planned to complete works on governing ring in June, and in July to complete assembly of distributor.

For Seredniodniprovska HPP (station No1) workshop No83 has assembled runner and is finishing final cutting of blades. According to plans, production will assemble runner for functional tests this month. Work on distributor continues.

Distributor and runner for Kaniv HPP (station 18) are delivered to customer.

Runner chamber has been manufactured and delivered to the customer for Kremenchug HPP (station No4): embedded parts are ready for shipment.

It will be recalled that rehabilitation of Ukrainian HPPs is carried out at the expense of European banks. In particular, “Turboatom” together with
“Elektrovazhmash” implements a number of projects:

Kaniv HPP. In November 2016, “Turboatom” and “Ukrhydroenergo” signed a contract for modernization of two units of the power plant. In accordance with the contract, “Turboatom” develops design, project and technical documentation, as well as manufactures and supplies 7 hydraulic turbines of ПЛ 15-ГК-600 in complete set for rehabilitation of two units of Kaniv HPP.

Kyiv PSPP. Contract for rehabilitation of three units of the power plant was signed between “Turboatom” and “Ukrhydroenergo” on 30 December 2016. “Turboatom” acted as general contractor for the “turnkey” project. For power plant “Turboatom” develops documentation, conducts model tests and supply to power plant three Francis type hydraulic turbines type PO75-B-300, conducts dismantling, installation, precommissioning and commissioning.

Seredniodniprovska HPP. Contract for rehabilitation of two hydraulic units (Kaplan type turbines and generators) was concluded on 22 November 2017 between “Turboatom” and “Ukrhydroenergo”. Implementation of the contract is scheduled up to September 2021.

Dnipro-2 HPP. Contract for rehabilitation of two hydraulic units (Kaplan type turbines and generators) was concluded on 22 November 2017 between “Turboatom” and “Ukrhydroenergo”. Implementation of the contract is scheduled up to May 2021.

Kremenchug HPP - Contract for rehabilitation of Kaplan type turbines was concluded between “Turboatom” and “Ukrhydroenergo” on 14 March 2019. Subject of the contract is rehabilitation of two turbines and two generators of hydraulic units. Nos 4, 5, including design, manufacture, supply of equipment, dismantling and installation works and engineering support services.