EN
UA

"Turboatom" is working on equipment for HPP

10.07.2020

Work on equipment for Ukrainian hydro power plants is underway in "Turboatom's" workshops.

In workshops of JSC "Turboatom" production of main assemblies for hydraulic unit of Kaniv HPP (station No 20) continues. Task of production for current month on this order is to prepare runner for functional tests and deliver it to customer.

Runner for Dnipro-2 HPP (station No 14) is completely delivered to customer and shipped to power plant. Production plans for July on this order are to complete work on governing ring. This will allow fully manufacture distributor, delivery of which to customer is scheduled for August 2020.

For Seredniodniprovska HPP (station No 1) workshop No 83 assembled runner and completed final cutting of blades. In June, runner was assembled for functional tests - arrival of representatives of customer is expected for acceptance. Next stage will be its balancing, after which runner will be prepared for shipment, scheduled for August-September of this year. Work on distributor continues.

In workshop No 83, work on assembling distributor for Kyiv PSPP (station No 4) continues. In particular, distributor prepared for installation of turbine head cover will be fully assembled and prepared for delivery to customer this month.

It will be recalled that rehabilitation of Ukrainian HPPs is carried out at the expense of European banks. In particular, "Turboatom" together with "Electrotyazhmash" implements a number of projects:

Kaniv HPP. In November 2016, "Turboatom" and "Ukrhydroenergo" signed a contract for modernization of two units of power plant. In accordance with the contract, "Turboatom" develops design, project and technical documentation, as well as manufactures and supplies 7 hydraulic turbines ПЛ 15-ГК-600 in complete set for rehabilitation of two power units of Kaniv HPP.

Kyiv PSPP. Contract for rehabilitation of three units of power plant was signed between "Turboatom" and "Ukrhydroenergo" on 30 December 2016. "Turboatom" acted as general contractor of "turnkey" project. For the power plant "Turboatom" develops documentation, conducts model tests and supplies to power plant three Francis type hydraulic turbines of the РО75-В-300type, performs dismantling, installation, pre-commissioning and commissioning.

Seredniodniprovska HPP. Contract rehabilitation of two hydraulic units (Kaplan type turbines and generators) was concluded on 22 November 2017 between "Turboatom" and "Ukrhydroenergo". Implementation of the contract is scheduled to September 2021.

Dnipro-2 HPP. Contract for rehabilitation of two hydraulic units (Kaplan type turbines and generators) was concluded on 22 November 2017 between "Turboatom" and "Ukrhydroenergo". Implementation of the contract is scheduled to May 2021.

Kremenchug HPP - contract for rehabilitation of Kaplan type turbines was concluded between "Turboatom" and "Ukrhydroenergo" on 14 March 2019. Subject of the contract is rehabilitation of two turbines and two generators of hydraulic units st. Nos 4, 5, including design, manufacture, supply of equipment, dismantling and installation works and engineering support services.