An agreement for the manufacture and supply of a condenser was signed

21.04.2021

On April 20, 2021, JSC “Turboatom” and SE NNEGC “Energoatom” signed an agreement for the manufacture and supply of a condenser for Zaporizhzhya NPP.

At the head office of SE NNEGC “Energoatom”, General Director of JSC ‘Turboatom” Viktor Subotin and Director of SS “Atomkomplekt” SE NNEGC “Energoatom” Oleg Doroshenko signed an agreement for the manufacture and supply of a modular condenser with pipe systems made of corrosion-resistant material of the turbine plant K- 1000-60/1500-2 for power unit No. 1 of Zaporizhzhya NPP.

The amount of the agreement signed with NNEGC “Energoatom” amounted to 525.8 million UAH. Equipment delivery time is April - May 2022.

Interim President of NNEGC “Energoatom” Petro Kotin noted: “This is a very important event for the Company. “Energoatom” has been confidently implementing the program of equipment modernization at 15 power units of four Ukrainian NPPs since August 2019 and designed for five years. New condensers are already in operation at three ZNPP units (No. 2, 3, 4). The production of a condenser for power unit No. 5 is nearing completion. Such works are planned for 2023 at power unit No. 6 of ZNPP. "

General Director of JSC “Turboatom” Viktor Subotin stressed that this is an important contract for turbine builders, because it means an order worth half a billion UAH and the workload of the enterprise for more than a year. “I am very grateful to “Energoatom” for their trust,” – added Victor Subotin.

Director of SS “Atomkomplekt” Oleg Doroshenko noted: “It is difficult to overestimate the significance of this agreement. The work on replacing the condensers has both an economic effect in the form of additional electricity generation and a technical one - increasing the reliability of power units operation.”

For Zaporizhzhya NPP, which consists of 6 power units with a capacity of 1000 MW, this will be the fifth new condenser out of six installed at the plant, which will replace “Turboatom”. Now the condensers are successfully operating at power units 2, 3 and 4. For unit No. 5, “Turboatom” is completing the manufacture of a condenser and in May-June 2021 the equipment will be fully shipped to the plant.